Location: Conshohocken, PA
Project Completion Date: October 2017
Client: Covanta Plymouth
Carylon Operating Company: Mobile Dredging & Video Pipe
Covanta had a scheduled full boiler outage in October 2017. The scope of work included ash removal in the baghouse area, sifting conveyers, ram and additional hopper cleaning throughout the facility. The work also included water blasting other key areas, so rehab work could be performed. These areas were the Quench reactor and the slurry tank. The surfaces were cleaned using water pressure of 10,000PSI to remove the accumulated ash and lime. All work was performed on time which resulted in on time facility start-up.